TESKOOP's history from its founding in 2005: expropriation, zoning plans, infrastructure works, the 2016 opening and the 2017 parcel allocation.
On 26 May 2005, 14 founding members signed the articles of association, prepared under Article 88 of Cooperatives Law No. 1163, at Istanbul 28th Notary with journal no. 17006, and the founding procedures began.
The founding Board of Directors consisted of Hasan Büyükdede, Sait Kılıç, Mehmet Nuri Görenoğlu, Mehmet Develioğlu and Erdoğan Torun. The founding Audit Board consisted of Mustafa Alkan and Adnan Alev.
On 1 June 2005, permission was obtained from the Istanbul Provincial Directorate of Industry and Trade under record no. 31814.
On 8 June 2005, the cooperative's articles of association were registered by the Istanbul Trade Registry Office under no. 556338 and published in the Trade Registry Gazette, and the cooperative became a legal entity.
On 13 June 2005, the cooperative applied to the S.S. İkitelli Small Industrial Sites Building Cooperatives Union and became a member by the Union Board's decision no. 225 of 13/07/2005.
On 20 September 2006, a contract was signed with Kuzey Müh. İnş. San. ve Tic. Ltd. to organize the procedures at the land registry, cadastre, municipality, TOKİ and other public institutions for the 1,100-decare site to be expropriated by TOKİ, and to provide technical consulting.
On 28 September 2006, TOKİ took an expropriation decision under Law No. 1164 for the area within Deliklikaya village, Hadımköy town, Çatalca district, Istanbul, and the Prime Ministry's approval was obtained.
On 22 November 2006, candidates applying for membership beyond the founding members were admitted for the first time by Board decision no. 27.
On 29 November 2006, a protocol was signed between TOKİ and the cooperative for expropriation on an advance-payment basis in Hadımköy Deliklikaya.
On 8 January 2007, a contract was signed with Attorney Mehmet Asmaoğlu to follow the legal process of the expropriation.
On 10 January 2007, an additional protocol to the TOKİ agreement was signed to follow the court proceedings relating to the expropriation area.
The legal process of the expropriation was followed and monitored throughout the year.
On 15 June 2009, the 1/100,000 Provincial Environmental Plan for the area was approved by Istanbul Metropolitan Municipality and came into force. The plan designated the area for industrial use.
From 15 May 2009, TOKİ began transferring the parcels whose expropriation process was complete to the cooperative by title deed. In this process, 1,059,323.66 m² of land was secured for the cooperative.
On 3 July 2009, a three-way protocol was signed with the S.S. Özar and S.S. Bahçeşehir cooperatives, agreeing that infrastructure investments in the Deliklikaya industrial area would be funded in proportion to each cooperative's land ownership in m².
On 29 January 2010, a protocol was signed with Armağan Müh. Danışmanlık for consulting on electricity supply and the design and construction of electricity distribution facilities.
A protocol was signed with BİMTAŞ for the design of the 1/5000 Revised Master Zoning Plan and the 1/1000 Implementation Zoning Plan.
In the 1/25,000 Northern Marmara Motorway Master Zoning Plan that came into force in September 2010, the motorway passes north of the project area, with access provided by a junction branch.
On 22 November 2010, the 1/5000 Hadımköy Area Master Zoning Plan was approved by Istanbul Metropolitan Municipality and came into force.
On 14 January 2011, the proposed 1/1000 Implementation Zoning Plan for Hadımköy Industrial Zone Phase 1 was approved. The project area lies partly in industrial, partly in commercial and amenity zones.
On 15 April 2011, the preliminary and final design of the roads and infrastructure was awarded to the Emi-İmar-Kemer joint venture.
On 1 July 2011, a protocol was signed with Emi Harita to follow the zoning readjustment procedures under Article 18 of Law No. 3194.
On 3 May 2012, supervision and consulting for the earthworks were awarded to Denge Altyapı Proje Müşavirlik ve İnşaat A.Ş.
On 18 April 2012, permission was obtained from Arnavutköy Municipality for the cooperative to build the roads within the Deliklikaya industrial area in line with the design.
On 9 May 2012, a 1/1000 plan amendment was approved by Arnavutköy Municipality Council Decision no. 48.
On 7 June 2012, the earthworks within the Deliklikaya industrial area were contracted to the Aksiyon-Gökkar joint venture.
On 21 February 2013, the cooperative took part in the tender for block 266, parcel 6, a 20,080.20 m² property offered for sale by decision of the Arnavutköy Municipality committee, and bought it.
The administrative building constructed on block 260, parcel 8, at Uyar Cad. No:22, DESB Industrial Zone, Hadımköy Deliklikaya, completed on 5 March 2013, was occupied on 10 May 2013.
On 24 June 2013, together with the S.S. Özar and S.S. Bahçeşehir cooperatives, an application was made to the Istanbul Governorship for the area to become a Private Organized Industrial Zone; the Governorship's approval was obtained on 05/07/2013.
The infrastructure works continued to be followed and monitored.
On 19 March 2015, a construction contract for road infrastructure, road surfacing, electricity infrastructure and other phase works was signed with the Aksiyon-Gökkar ordinary partnership.
On 4 June 2015, a natural gas infrastructure protocol was signed with Aksa Trakya Doğalgaz Dağıtım A.Ş.
On 12 October 2015, parcels 1 to 10 of block 316 within DESB were transferred by agreement to TEİAŞ on condition that a substation be built.
On 11 December 2015, a facility contract was signed with Boğaziçi Elektrik Dağıtım A.Ş.
The infrastructure works continued to be followed and monitored. Following the Ordinary General Assembly decision of 7 May 2016, work on the parcel lottery began.
On 16 August 2016, the cooperative took part in the Hadımköy Industry Fair organized by Arnavutköy Municipality, at stand no. 43.
On 20 September 2016, asphalt surfacing began on the roads whose infrastructure was complete.
On 30 September 2016, with 80% of its infrastructure complete, the Opening Ceremony of the DESB Industrial Zone was held with Minister of Industry Dr. Faruk Özlü, Istanbul Metropolitan Mayor Dr. Kadir Topbaş, members of parliament, industrialists and the press.
The infrastructure works continued to be followed and monitored.
On 26 January 2017, work began on 60 workplaces with a 500 m² footprint for existing members on block 294, parcel 1. Construction was planned to start in January 2018.
On 8 August 2017, a lottery was held to allocate industrial parcels totalling 662,803.92 m² across 284 parcels owned by the cooperative to 156 registered members.
On 9 August 2017, the industrial parcels allocated by lottery were handed over to the members.
On 1 November 2017, distribution of Title Allocation Certificates began for members allocated an industrial parcel by lottery.