TESKOOP Private Industrial Zone

Electricity Connection Application

Electricity connection application at TESKOOP: design approval, connection opinion, meter and energization steps.

Power infrastructure for parcels in the zone is planned at 160 kVA, and medium and low voltage lines are brought to each parcel entrance through the gallery. These are the steps to energize your facility:

  1. Determining power needsInstalled power and simultaneous use are calculated.
  2. Connection opinionAn application for a connection opinion is made to the distribution company.
  3. Electrical designThe internal installation design, and a transformer design if needed, is prepared and approved.
  4. Installation and acceptanceThe installation is completed and acceptance procedures are carried out.
  5. Meter and powerThe meter is installed, the subscription is opened and the facility is energized.

Documents required

  • Title deed or a document showing the right of use
  • Building permit or occupancy permit
  • Approved electrical design
  • Tax certificate and signature circular

For facilities with high power demand, we recommend speaking with our technical services unit before applying.